We are pleased to announce Solaria has obtained the favourable feasibility access permit (IVA) to install 782.5MW PV in Villaviciosa de Odón 400kV substation located in Madrid province, where Solaria acts as Single Node Interlocutor (IUN).

In addition, it has obtained the favourable feasibility access permit to install 180MW PV in Mangraners (where Solaria acts also as Single Node Interlocutor (IUN)) and Albatarrec 220kV substations, both located in Lleida province.

Both  will generate an estimated production of 1900GWh per year equivalent to the consumption of a population of 580,000 and will prevent the emission of 388,000 tons of CO2 per year.

Villaviciosa PV Complex is the biggest project in Solaria’s portfolio and along with Lleida Complex represent 29% of the 3,325MW target set by the company for 2023.

Including the 626MW Trillo Complex (announced in 2019), it represents 48% of the 2023 target of the company.

LAST NEWS

April 2020

Solaria will install more than 2,500MW in Castilla-La Mancha in the next two years

April 2020

SOLARIA ENTERS IN THE IBEX 35

April 2020

1H20 RESULTS PRESENTATION & CAPITAL MARKETS DAY - 6.2GW by 2025

April 2020

SOLARIA SIGNS A 150WM PPA WITH THE SWISS COMPANY AXPO FOR 10 YEARS

COME BACK

BUSINESS

Discover our solutions in action

GENERATION

SOLARIA manages and operates photovoltaic plants with a total generation capacity of more than 410 MW.

SEE MORE

FUTURE PROJECTS

SOLARIA has a pipeline of more than 10,000 MW of potentially developable projects distributed in Iberia.

SEE MORE